Home > 건축 및 환경⋅플랜트 > PERU Hydro Power Plant
Huertas Hydroelectric Power Plant in Huanuco State, Peru (Private inverstment Project)
- Huertas, Huanuco state, Peru
WKE&C is building a new hydro power plant of improved quality which will reduce the chance of disrupted ecology which is accomplished by abundant experience in constructing domestic and overseas power plants using hydro power energy.
> Small Hydropower generation facility at I-Po Dam
Client : Korea Water Resources Corporation | |
Contractor : Daelim Co., Ltd. APC Co., Ltd. | |
1. Capacity : 3,200㎾ class (1,067㎾ x 3 UNIT) 2. Type : Horizontal shaft type, Kaplan hydro turbine, Synchronous generator 3. Conents : 1) Turbine & Generator 2) Control System 3) Auxiliary facility 4) Commissioning * Turbine Generator Maker : MAVEL |
> Cheongpyeong Hydropower #4 new UNIT
Client : Korea Hydro & Nuclear Power Co., Ltd | |
Contractor : Sambu | |
1. Capacity : 60MW class Cheongpyeong hydro power plant #4 new mechanical work 2. Type : Vertical shaft Kaplan turbine, inductive generator 3. Conents : Hydro turbine and generator, Installation of auxiliary equipment & spiral casing, Supply & Erection of penstock |
> Hydro Power Plant(900kW x 6 UNIT) construction for Sampo Thermal Power Plant
Client : Korea South East Power Co., Ltd. | |
Contractor : Halla Energy & Environment | |
1. Civil construction : 3,200㎾ class (1,067㎾ x 3 UNIT) 1) Installation of intake gate during dam construction 2) Construction of reinforced steel structure during cofferdam and preparatory construction 3) Power transmission line 2. Building : Horizontal shaft type, Kaplan hydro turbine, Synchronous generator 3. Installation of turbine and generator : 1) Installation of steel structure 2) Installation of intake gate |
> Small Ocean Hydro Power Plant construction for Taean Thermal Power Plan
Client : Korea Western Power Co., Ltd. | |
Contractor : Hwachon Plant | |
1. Structure and earth work 2. Hydro turbine and generator: Installation of 550㎾ x 4 UNIT 3. Entrance valve gate: Installation of 4 SET 4. Transformer. Switchgear 5. Control facility UPS facility 6. Monorail Hoist 7. 22.9㎸ power transmission line 8. Commissioning |